Primary Runway Closes as Jonesboro Airport Construction Advances

JONESBORO, Ark. — The primary runway at Jonesboro Municipal Airport closed this month as construction moved into its next phase, airport officials announced.

The runway project is approximately 50% complete and is expected to reopen by Oct. 1. Airport operations are continuing on the secondary runway, allowing business to proceed as usual during construction.

Work also continues on the airport’s new terminal, which is approximately 40% complete. Crews are installing climate-control systems and electrical infrastructure.

Weather delays have pushed the terminal project beyond its original November completion target. Officials did not announce a revised completion date.

The airport’s new hangars are approximately 50% complete and remain on schedule to be finished by Oct. 1.

This slideshow requires JavaScript.


Discover more from NEA Report

Subscribe to get the latest posts sent to your email.

Submit a Correction

Accuracy matters. If you believe something in this story is incorrect, please tell us so our newsroom can review it.

Report an error in this story

About this story: Primary Runway Closes as Jonesboro Airport Construction Advances
https://neareport.com/2026/07/31/primary-runway-closes-as-jonesboro-airport-construction-advances/

Your submission is private and will not appear as a comment. The story title and link are included automatically.

What do you think?

Discover more from NEA Report

Subscribe now to keep reading and get access to the full archive.

Continue reading